Project Description

Covid-19 Works At Lancaster Hospital

We were contacted by Main Contractor Carefoot Construction to work with them on urgent Covid19 Works, commencing work on site within days of the initial call.

The emergency works were required to convert Ward 16 to Children’s Ward facilities so the existing Children’s Ward could be made available as a Covid19 Ward to enable segregation of Covid19 Patients.

Works were completed over the weekend and the course of the following week to enable the transfer of services as soon as possible so that the ward could be utilised immediately.

  • Installation of new power for new Bed Head containment and associated services
  • Modifications to existing distribution
  • Installation of new CCTV
  • Installation of data

We received the following comments from the Project Engineer:

  • Ward relocation for Covid-19

  • Emergency Works completed over 8 day period

  • Working with Main Contractor Carefoot Construction

FEEDBACK

I would personally like to pass on my thanks to you and team, they have been fantastic.  The press and social media have been rightly full of praise for the NHS heros, as far as II am concerned that includes your team too, what they have achieved in such a short time has been amazing”

Paul Kershaw, Project Engineer

Estates Capital Services

GALLERY

Ask Us

We would be happy to discuss any aspect of your project and how we can help.
Get in touch with us today

Contact Us