Future-Proofing Quernmore CE Primary School Through a Complete Electrical Infrastructure Upgrade

  • Client: Lancashire County Council

  • Sector:Education

  • Project Duration: 6 months

  • Scope: Electrical

  • Value:£180,000

Project Overview

Thompson Building Services Engineers successfully delivered a comprehensive electrical infrastructure upgrade at Quernmore CE Primary School on behalf of Lancashire County Council.

The seven-month programme involved far more than a traditional rewire. The project included the upgrade of the school’s incoming electricity supply, relocation of the main intake position, replacement of distribution equipment, installation of new LED lighting, upgraded emergency lighting, a new addressable fire alarm system, modern data infrastructure and associated electrical improvements throughout the school.
Working within a live educational environment required careful planning and close coordination with school staff to ensure teaching activities could continue safely throughout the works programme.
The completed installation provides the school with a safer, more reliable and energy-efficient electrical infrastructure designed to support current and future operational requirements.

The Challenge

Like many older school buildings, Quernmore CE Primary School required significant investment in its electrical infrastructure to meet modern operational demands.

The project needed to:
  • Upgrade the incoming electricity supply to support future demand
  • Replace ageing electrical distribution equipment
  • Improve electrical safety and system resilience
  • Modernise lighting throughout teaching and circulation spaces
  • Upgrade emergency lighting and fire alarm systems
  • Improve ICT and data connectivity
  • Minimise disruption to staff, pupils and day-to-day school operations
  • Maintain a safe and secure learning environment throughout construction works
Because the school remained operational during the project, careful phasing and stakeholder communication were essential to successful delivery.

A Complete Electrical Modernisation

A key element of the project was the installation of a new incoming electrical supply and upgraded main switchgear infrastructure.

The existing electrical arrangements were reorganised and modernised through the installation of new Schneider distribution equipment, metered distribution boards and upgraded power distribution systems. The works significantly improved capacity, monitoring capability and future flexibility across the site. Power circuits were installed throughout the school alongside dedicated supplies for specialist equipment, ICT infrastructure, life-safety systems and mechanical services.
The completed electrical infrastructure now provides a robust foundation for the school’s continued development.

Energy Efficient Lighting for Modern Learning

As part of the upgrade, new LED lighting was installed throughout classrooms, corridors, offices, communal spaces and circulation areas. The scheme utilised modern Southgate Lighting luminaires combined with intelligent lighting controls to improve both energy efficiency and user comfort.
The lighting control strategy incorporates:
  • Presence and absence detection
  • Dimming functionality
  • Intelligent lighting management
  • Improved lighting quality within teaching spaces
  • Reduced energy consumption compared with older systems
The result is a brighter, more adaptable environment that better supports learning while helping reduce operational energy demand.

Strengthening Safety and Compliance 

Life-safety improvements formed an important part of the overall project.   The existing fire alarm system was upgraded with a new addressable C-TEC system incorporating revised device addressing, improved zoning and updated control equipment.
The project also included:
  • New emergency lighting installations
  • Illuminated exit signage
  • Upgraded fire alarm devices
  • Enhanced system monitoring and control
  • Full testing and commissioning in accordance with current standards

Supporting Digital Learning

Modern schools require dependable digital infrastructure alongside reliable electrical services. The project therefore included the installation of upgraded ICT infrastructure, data outlets and wireless connectivity provisions throughout the building. New data installations were coordinated with the wider electrical package to support teaching technology, administration systems and future digital requirements.

Delivering in a Live School Environment

One of the project’s greatest challenges was delivering significant infrastructure upgrades within an occupied primary school.

The Thompson team worked closely with Lancashire County Council and school representatives throughout the programme, carefully coordinating activities to minimise disruption to teaching and safeguarding requirements.
Phased working, effective communication and collaborative planning enabled the project to progress safely while maintaining day-to-day operation of the school.
This approach played a key role in achieving a successful outcome and maintaining positive relationships with all stakeholders.

FEEDBACK

The professionalism, coordination and collaborative approach demonstrated throughout the project were recognised by both school representatives and wider project stakeholders following completion.

Feedback received after handover praised the management of the works from start to finish and highlighted the effective partnership between the project team, school staff and contractors. Stakeholders commented positively on both the delivery process and the quality of the finished installation, reflecting the commitment of everyone involved in the scheme.
For projects delivered within live educational environments, this level of stakeholder confidence is every bit as important as the technical achievement itself.

GALLERY

Delivering a full electrical infrastructure upgrade within an operational school requires more than technical expertise alone. It demands planning, communication and a commitment to working collaboratively with everyone involved.

This project demonstrates Thompson’s ability to undertake complex electrical infrastructure upgrades in occupied environments while maintaining the highest standards of safety, quality and client care.
It’s The Thompson Way: trusted delivery, practical engineering and infrastructure built for the future.
Contact Us